PLANT: Turnkey industrial biogas plant for OFMSW and sewage sludge
KEY FIGURES: 900 Nm³ biogas; 2 MW electricity; 250 t/d of input material
PROJECT: EPC project, 2 separate treatment lines, construction start: 2019, commissioning: 2021
PLANT: Turnkey industrial biogas plant for OFMSW and sewage sludge
KEY FIGURES: 900 Nm³ biogas; 2 MW electricity; 250 t/d of input material
PROJECT: EPC project, 2 separate treatment lines, construction start: 2019, commissioning: 2021